Construction Update 10/23/17

Music, Art & Spec Ed/Shops Buildings (F, I , G, & D Restrooms)

1) Two Story Main Building D Boys & Girls Restrooms - Ceramic tile correction work took place Friday and Saturday, temporary exhaust fans were installed Saturday.  Restrooms were turned over to the District on Monday, October 23.  Remaining - Painting is scheduled for next week after hours.

2) Andy Gump Portable Restrooms will be removed by the morning of Wednesday, October 25.  The area will be cleaned with a pressure washer on Wednesday as well.

3) Kiln Room - Exhaust fan installation, fire stopping around penetrations, and some drywall took place Saturday.  Kiln was turned over to the District on Monday, October 23.  Remaining - Painting scheduled for next week and Fire Damper installation scheduled within next two weeks and campus fire watch to remain in place.

4) Dark Room (temporary renovation due to mold discovery) - Construction Change Directive received from HMC Architects on Tuesday, October 17th, Angeles Construction Inc. is currently reviewing/pricing the CCD.  Once we receive the change order proposal, work is expected to be completed within two weeks.

5) Art Building I - Mechanical ductwork (not part of original scope) - exhaust fans, fire dampers furnace expected to be received within 5 weeks, installation to follow immediately thereafter

6) Special Ed/Shops Building G - Special Education Room - ACI expects to receive the casework (additional work not part of original scope) this week and installed by the end of the week.

7) Punchlist Items in Progress

Phase 1 & 2

1) Parking Lot E - On schedule, we are installed base on Friday!!!  





2) Buildings B & C - On hold, Awaiting direction from the District on how to proceed with regards to the disposal of the concrete slab containing PCBs

3) MDF - On hold, Awaiting on the redesign of the MDF at new location

There has been significant progress made over the last couple of months and we are nearing the finish line as we continue to work with the Contractor to complete the work.  