Construction Update 10/23/17

Image
Music, Art & Spec Ed/Shops Buildings (F, I , G, & D Restrooms) 1) Two Story Main Building D Boys & Girls Restrooms - Ceramic tile correction work took place Friday and Saturday, temporary exhaust fans were installed Saturday.  Restrooms were turned over to the District on Monday, October 23.  Remaining - Painting is scheduled for next week after hours. 2) Andy Gump Portable Restrooms will be removed by the morning of Wednesday, October 25.  The area will be cleaned with a pressure washer on Wednesday as well. 3) Kiln Room - Exhaust fan installation, fire stopping around penetrations, and some drywall took place Saturday.  Kiln was turned over to the District on Monday, October 23.  Remaining - Painting scheduled for next week and Fire Damper installation scheduled within next two weeks and campus fire watch to remain in place. 4) Dark Room (temporary renovation due to mold discovery) - Construction Change Directive received from HMC Architects on Tuesday, October 1